F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

A130/5 days

B106/7 days

C114/7 days

D120/7 days

Answer:

D. 120/7 days

Read Explanation:

Solution: Given: Time taken by F alone = 24 days Time is taken by G alone = 32 days G leaves the work 8 days before the completion of work Formula Used: Total work = Time taken × Efficiency Calculation: Let the total work be LCM of 24 and 32 i.e. 96 unit Work done by F in 1 day = 96/24 = 4 unit Work done by G in 1 day = 96/32 = 3 unit G leaves the work 8 days before the completion of work, so F worked alone for 8 days Work done by F in 8 days = 4 × 8 = 32 unit Work left = 96 - 32 = 64 unit 64 unit work is done by both G and F Time taken to complete 64 unit work = 64/(4 + 3) = 64/7 days ∴ Total time taken = 8 days + 64/7 days = 120/7 days


Related Questions:

If the first and second letters in the word 'COMMUNICATIONS' were interchanged, also the third and the fourth letters, the fifth and sixth letters and so on, which letter would be the tenth letter counting from your right?
ഒരു ടാങ്ക് നിറയാൻ മൂന്ന് പൈപ്പുകൾ 1 മണിക്കൂർ 30 മിനിറ്റ് എടുക്കും എന്നാൽ രണ്ടു പൈപ്പുകൾ ഉപയോഗിക്കുന്നത് വഴി ടാങ്ക് നിറയുവാൻ എത്ര സമയം വേണ്ടിവരും ?
51 men can complete a work in 12 days. Four days after they started working 6 more men joined them. How many days will they now take to complete the remaining work?
A can do a piece of work in 5 days, B in 10 days. How long will they take to do it together?
The working efficiency of Ram, Shyam and Shiva is 4 : 2 : 1. Shiva alone can complete the work in 100 days. If Ram and Shyam work together for 16 days and leave, then find the number of days required by Shiva to complete the remaining work.