F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

A130/5 days

B106/7 days

C114/7 days

D120/7 days

Answer:

D. 120/7 days

Read Explanation:

Solution: Given: Time taken by F alone = 24 days Time is taken by G alone = 32 days G leaves the work 8 days before the completion of work Formula Used: Total work = Time taken × Efficiency Calculation: Let the total work be LCM of 24 and 32 i.e. 96 unit Work done by F in 1 day = 96/24 = 4 unit Work done by G in 1 day = 96/32 = 3 unit G leaves the work 8 days before the completion of work, so F worked alone for 8 days Work done by F in 8 days = 4 × 8 = 32 unit Work left = 96 - 32 = 64 unit 64 unit work is done by both G and F Time taken to complete 64 unit work = 64/(4 + 3) = 64/7 days ∴ Total time taken = 8 days + 64/7 days = 120/7 days


Related Questions:

If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?
Midhun writes the numbers 1 to 100. How many times does he write the digit'0' ?
A ഒരു നിശ്ചിത ജോലി 4 മണിക്കൂർ കൊണ്ട് ചെയ്യാൻ കഴിയും. A യും B യും ചേർന്ന് ഒരേ ജോലി 2 മണിക്കൂർ കൊണ്ട് ചെയ്യുന്നു. B യും C യും ചേർന്ന് 3 മണിക്കൂറിനുള്ളിൽ ഇത് ചെയ്യുന്നു. C മാത്രം ജോലി ചെയ്യാൻ എത്ര സമയമെടുക്കും?
A and B undertake to do a piece of work for Rs. 330. A can do it in 11 days and B can do it in 22 days. With the help of C, they finish it in 6 days. How much should C be paid for his work?
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?