Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is

A36

B48

C45

D32

Answer:

B. 48

Read Explanation:

Ganesh, Ram and Sohan together can complete a work in 16 days

Ganesh and Ram together can complete the same work in 24 days,

Total work = LCM(16, 24) = 48

efficiency of Ganesh, Ram and Sohan = 48/16 = 3

Efficiency of Ganesh and Ram = 48/24 =2

Efficiency of Sohan = 3 - 2 = 1

The number of days Sohan alone takes, to finish the work = total work/ efficiency of sohan = 48/1 = 48 days


Related Questions:

A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will B alone complete 20% of the remaining work?
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?
A, 6 ദിവസം കൊണ്ടും B, 12 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. ഒരുമിച്ചു പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് ജോലി തീരും?
9 കുട്ടികൾക്ക് 360 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. 18 പുരുഷന്മാർക്ക് ഇതേ ജോലി 72 ദിവസം കൊണ്ടും 12 സ്ത്രീകൾക്ക് 162 ദിവസം കൊണ്ടും പൂർത്തിയാക്കാനാകും. 4 പുരുഷന്മാരും 12 സ്ത്രീകളും 10 കുട്ടികളും ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?