Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is

A36

B48

C45

D32

Answer:

B. 48

Read Explanation:

Ganesh, Ram and Sohan together can complete a work in 16 days

Ganesh and Ram together can complete the same work in 24 days,

Total work = LCM(16, 24) = 48

efficiency of Ganesh, Ram and Sohan = 48/16 = 3

Efficiency of Ganesh and Ram = 48/24 =2

Efficiency of Sohan = 3 - 2 = 1

The number of days Sohan alone takes, to finish the work = total work/ efficiency of sohan = 48/1 = 48 days


Related Questions:

24 people can finish a job by 10 days. How many days will be required to finish the same job by 8 people?
12 പേർ 24 ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി 16 പേർ എത്ര ദിവസംകൊണ്ട് തീർക്കും ?
Tripti can construct a divider alone in 4 days while Rajan can construct it alone in 3 days. If they construct it together and get a payment of Rs. 14000, then what is Tripti's share?
20 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി ചെയ്യാൻ 10 പേർക്ക് എത്ര ദിവസം വേണം ?
രാമു ഒരു ജോലി 6 ദിവസം കൊണ്ട് ചെയ്യും. രമ അതേ ജോലി ചെയ്യാൻ 8 ദിവസം എടുക്കും. എന്നാൽ രണ്ടുപേരും ഒരുമിച്ച് ജോലി ചെയ്താൽ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം ?