App Logo

No.1 PSC Learning App

1M+ Downloads
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

Sankar and Vishnu work alternately in a tailoring shop on an order of stitching 21 suits. Sankar starts the work, stitches 3 suits in two days, and takes a break, during which Vishnu stitches 3 suits in three days, and then takes a break. This pattern is repeated till all the 21 suits are stitched. How many days did it take the duo to complete the work?
A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?
എ, ബി എന്നിവർ ചേർന്ന് ഒരു പണി 12 ദിവസം കൊണ്ടു വര്സിക്കുന്നു. ബി, സി 15 ദിവസവും, എ, സി 20 ദിവസവും കൊണ്ട്. എ, ബി, സി മൂന്ന് പേരും ചേർന്ന് പണി നടത്തി തികയ്ക്കാൻ എത്ര ദിവസം?
12 men and 16 women can complete a job in 5 days. 13 men and 24 women can complete the same job in 4 days. How long in days, will 5 men and 10 women take to complete the same job?
One pipe can fill the tank in 20 min while another pipe can empty it in 60 min. If both the pipes are operated together, how long will it take to fill the tank completely?