App Logo

No.1 PSC Learning App

1M+ Downloads
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

10 പുരുഷന്മാർ ഒരു ജോലി 12 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ കഴിയുമെങ്കിൽ അതെ ജോലി ചെയ്യാൻ 12 പുരുഷന്മാർ എടുക്കുന്ന സമയം എത്ര?
ഒരു ജോലി ചെയ്ത് തീർക്കാൻ 16 പേർക്ക് 30 ദിവസം വേണം. എന്നാൽ 20 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം?
ഒരു ക്ലോക്കിൽ സമയം 8:20 pm കാണിക്കുന്നു എങ്കിൽ മിനിറ്റു സൂചിയും മണിക്കൂർ സൂചിയും തമ്മിലുള്ള കോണളവ് എത്ര ?
K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank if the capacity of each bucket is 9 litres?