App Logo

No.1 PSC Learning App

1M+ Downloads
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

മൂന്നു സംഖ്യകളുടെ അനുപാതം 3:5 :7 ആണ്.ആദ്യത്തെ സംഖ്യയും മൂന്നാമത്തെ സംഖ്യയും കൂട്ടിയാൽ രണ്ടാമത്തെ സംഖ്യയേക്കാൾ 40 കൂടുതലാണെങ്കിൽ ,ഏറ്റവും വലിയ സംഖ്യ എത്ര ?
Two pipes A and B can fill a tank in 6 hours and 8 hours respectivley. If both the pipes are opened together, then after how many hours should B be closed so that the tank is full in 4 hours ?
A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
The working efficiency of Raja, Ram and Mohan is 6 : 3 : 2. Raja can complete the whole work in 10 days. Raja and Ram together work for the first two days and then Raja and Mohan work for next 4 days and the remaining work is completed by Mohan. Find the total time taken to complete the work.
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in: