Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

8 men can complete a piece of work in 8 days while 8 women can do it in 12 days. In how many days can 2 women and 4 men complete it?
ഒരു പ്രത്യേക ജോലി ചെയ്തു തീർക്കാൻ അജയന് 6 ദിവസം വേണ്ടിവരും. അതേ ജോലി ചെയ്തു തീർക്കാൻ വിജയന് 3 ദിവസം മതിയാകും. രണ്ടുപേരും കൂടി ഒരേസമയം ഈ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം വേണം ?
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?
20 ആളുകൾ 6 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 8 ആളുകൾ എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?