Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

A യ്ക്ക് 15 ദിവസം കൊണ്ടും B യ്ക്ക് 20 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. അവർ 4 ദിവസത്തേക്ക് ഒരുമിച്ച് ജോലി ചെയ്യുകയാണെങ്കിൽ, ശേഷിക്കുന്ന ജോലിയുടെ അംശം?
A യ്ക്ക് 18 ദിവസവും B 20 ദിവസവും C 30 ദിവസവും കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ ക ഴിയും. B യും C യും ചേർന്ന് ജോലി ആരംഭിക്കുകയും 2 ദിവസത്തിന് ശേഷം പോകാൻ നിർബന്ധിതരാവുകയും ചെയ്യുന്നു. ശേഷിക്കുന്ന ജോലി പൂർത്തിയാക്കാൻ A മാത്രം എടുക്കുന്ന സമയം
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
One pipe can fill a tank three times as fast as another pipe. If together the two pipes can fill the tank in 36 minutes, then the slower pipe alone will be able to fill the tank in :
രമ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കും. രമണി അതേ ജോലി 18 ദിവസം കൊണ്ട് തീർക്കും. രാജുവും രമയും രമണിയും കൂടി ഈ ജോലി 4 ദിവസം കൊണ്ട് തീർക്കും. എന്നാൽ രാജുവിന് ഈ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം ?