App Logo

No.1 PSC Learning App

1M+ Downloads
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

24 സെ.മി ഉയരവും 6 സെ.മി ബേസ് റേഡിയസുമുള്ള ഒരു കോൺ ഉരുക്കി ഒരു ഗോളത്തിന്ടെ രൂപത്തിൽ പുനർ രൂപകൽപന ചെയ്തിരിക്കുന്നു. എങ്കിൽ ആ ഗോളത്തിന്ടെ ആരം എത്രയാണ് ?
Anu can type 40 pages of a book in 10 hours. Anu and Mohit together can type 270 pages in 54 hours. In what time (in hours) can Mohit alone type 20 pages?
Jitesh and Kamal can complete a certain piece of work in 7 and 16 days, respectively, They started to work together, and after 2 days, Kamal left. In how many days will Jitesh complete the remaining work?
A യും B യും ചേർന്ന് 24 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും. 40 ദിവസത്തിനുള്ളിൽ A ക്ക് തനിച്ച് ഈ ജോലി ചെയ്യാൻ കഴിയും. എത്ര ദിവസത്തിനുള്ളിൽ B ഒറ്റയ്ക്ക് ജോലി ചെയ്തു തീർക്കും ?
30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond in 20 days?