App Logo

No.1 PSC Learning App

1M+ Downloads
If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?

A24 days

B15 days

C8 days

D18 days

Answer:

D. 18 days

Read Explanation:

Solution: Given: C alone can complete two-third part of a work in 12 days Concept: If a person can complete (x/y) part of a work in z days, then the person can complete the whole work in {z × (y/x)} days Calculation: 2/3 part → 12 days ⇒ 1 part → 12 × (3/2) = 18 days ∴ C can complete the whole work in 18 days


Related Questions:

A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C, B alone can do the work in:
Two pipes are connected to a water tank. The first pipe can fill the tank in 10 minutes and the second pipe can empty it in 15 minutes. If both pipes opened simultaneously, then find the time in which the tank will be completely filled with water.
32 പേർ 6 മണിക്കൂർ വീതം ജോലി ചെയ്താൽ 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കുന്ന ഒരു ജോലി 24 പേർ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ ഒരു ദിവസം എത്ര മണിക്കൂർ ജോലി ചെയ്യണം?
6/7 part of a tank is filled with oil. After taking out 60 litres of oil the tank is 4/5 part full. What is the capacity (in litres) of the tank?

A can complete 331333\frac{1}{3} % of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in: