App Logo

No.1 PSC Learning App

1M+ Downloads
If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?

A24 days

B15 days

C8 days

D18 days

Answer:

D. 18 days

Read Explanation:

Solution: Given: C alone can complete two-third part of a work in 12 days Concept: If a person can complete (x/y) part of a work in z days, then the person can complete the whole work in {z × (y/x)} days Calculation: 2/3 part → 12 days ⇒ 1 part → 12 × (3/2) = 18 days ∴ C can complete the whole work in 18 days


Related Questions:

A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work?
A man running at a speed of 15 km/hr crosses a bridge in 3 minutes. What is the length of the bridge?
"A' ഒരു ജോലി 20 ദിവസം കൊണ്ടും "B' അതേ ജോലി 30 ദിവസം കൊണ്ടും ചെയ്തുതീർക്കും. A യും B യും ഒരുമിച്ച് ആ ജോലി ചെയ്യുകയാണെങ്കിൽ എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാകും?
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
A ഒരു നിശ്ചിത ജോലി 4 മണിക്കൂർ കൊണ്ട് ചെയ്യാൻ കഴിയും. A യും B യും ചേർന്ന് ഒരേ ജോലി 2 മണിക്കൂർ കൊണ്ട് ചെയ്യുന്നു. B യും C യും ചേർന്ന് 3 മണിക്കൂറിനുള്ളിൽ ഇത് ചെയ്യുന്നു. C മാത്രം ജോലി ചെയ്യാൻ എത്ര സമയമെടുക്കും?