If John can complete a job in 8 hours and Sara can complete the same job in 12 hours how long will it take them to complete the job together ?

A5 hours

B6⅔ hours

C4⅘ hours

D7½ hours

Answer:

C. 4⅘ hours

Read Explanation:

total work = lcm(8, 12) = 24 efficiency of John = 24/8 = 3 efficiency of Sara = 24/12 = 2 efficiency of John and Sarah together = 3 + 2 = 5 the time taken by Sara and join to complete the job together = total work / efficiency = 24/5 = 4⅘


Related Questions:

A can do a piece of work in 12 days. B can do it in 18 days. With the assistance of C, they completed the work in 4 days. C alone can do it in ______________days.
A ക്ക് ഒരു ജോലി 6 ദിവസം കൊണ്ടും B ക്ക് 4 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
Kartik can do a piece of work in 4 hours. Ishan can do it in 20 hours. With the assistance of Krish, they completed the work in 2 hours. In how many hours can Krish alone do it?
ജോണും ദീപുവും ചേർന്ന് ഒരു ജോലി ചെയ്തു തീർക്കാൻ 45 ദിവസം എടുക്കുന്നു.എന്നാൽ ജോൺ ഒറ്റയ്ക്ക് ഈ ജോലി 70 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ദീപു ഒറ്റയ്ക്ക്ഇതേ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും?
"A' ഒരു ജോലി 20 ദിവസം കൊണ്ടും "B' അതേ ജോലി 30 ദിവസം കൊണ്ടും ചെയ്തുതീർക്കും. A യും B യും ഒരുമിച്ച് ആ ജോലി ചെയ്യുകയാണെങ്കിൽ എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാകും?