Negative slack occurs when -

AEvents stick to their schedule

BDummy activities are large in number

CActivities lie in critical path

DThere is deficiency of resources

Answer:

D. There is deficiency of resources

Read Explanation:

Negative slack occurs when the latest allowable occurrence time (TL) is less than the earliest expected time (TE), indicating the project is behind schedule due to a lack of resources. Slack time can be calculated using the equation Slack = TL - TE. Positive slack indicates the project is ahead of schedule with excess resources, while zero slack means the project is on schedule with adequate resources.