If P and Q together can do a job in 15 days, Q and R together can do it in 12 days and P and R together can do the same in 20 days, then in how many days will the job be completed, if all the three work together?

A4 days

B6 days

C10 days

D14 days

Answer:

C. 10 days

Read Explanation:

image.png

60 is the total work

4 and 5 and 3 are efficiency respectively

worktime=efficiency\frac{work}{time} = efficiency

so total efficiency together is 12

2(A+B+C)=4+5+3=12

(A+B+C)=12/2=6

so if all the three work together the no of days

=60/6=10 days


Related Questions:

A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:
Two pipes X and Y can fill a cistern in 24 minutes and 32 minutes respectively. If both the pipes are opened together, then after how much time (in minutes) should Y be closed so that the tank is full in 18 minutes ?
മനുവിന് ഒരു ജോലി ചെയ്യാൻ 10 ദിവസം വേണം അനുവിന് അത് ചെയ്ത് തീർക്കാൻ 15 ദിവസം വേണം. എങ്കിൽ രണ്ടു പേരും ചേർന്ന് ഈ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?
A ഒരു ജോലി 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. അതേ ജോലി B, 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. എന്നാൽ A യും B യും ചേർന്ന് ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാം?
A bicycle is sold at a profit of 10%. Had it been sold for 900 less, there would have been a loss of 10%. The cost price of the bicycle is: