Challenger App

No.1 PSC Learning App

1M+ Downloads
Pipes A, B and C can fill a tank in 10, 15 and 18 hours, respectively. A and C are opened for 5 hours, then only pipe A is closed and B is opened at the same time (with C). The total time taken to fill the tank completely is:

A3323\frac{3}{2}

B69116\frac{9}{11}

C58115\frac{8}{11}

D2132\frac{1}{3}

Answer:

69116\frac{9}{11}

Read Explanation:

Solution:

Formula:

Efficiency = Total work done/ total time taken

Calculation:

Let the volume of the tank

⇒ LCM of 5, 10, 15, and 18 = 90 units

Efficiency of A = 90/10 = 9 units/hr

Efficiency of B = 90/15 = 6 units/hr

Efficiency of C = 90/18 = 5 units/hr

Total volume filled by A and C in 5 hours

⇒ (9 + 5) × 5 = 70 units

Remaining volume = 90 - 70 = 20 units

 

Total volume filled by B and C in 1 hour

⇒ 6 + 5 = 11 units/hr

Time taken to fill the remaining volume by B and C

2011=1911\frac{20}{11}=1\frac{9}{11}

Time taken to fill the complete tank =5+1911=6911= 5 +1\frac{9}{11}=6\frac{9}{11}hours

The total time taken to fill the tank  is 69116\frac{9}{11}hours.


Related Questions:

The efficiency of A, B, and C is 2 : 3 : 5. A alone can complete a work in 50 days. They all work together for 5 days and then C left the work, in how many days A and B together can complete the remaining work?
രേഖയ്ക്കും സൊണാലിക്കും 20 ദിവസത്തെ കൂലിയായി ലഭിച്ചത് 2800 രൂപയാണ്. സൊണാലിയുടെ മൂന്നിരട്ടിയായിരുന്നു രേഖയുടെ ജോലിയിലെ കാര്യക്ഷമത. സൊണാലിയുടെ ദിവസ വേതനം എത്രയാണ്?
Vijayan can do a job in 25 days and Achyuth can do it in 20 days. Vijayan started the work and Achyuth joined af. ter 15 days and Vijayan left. How many days did Achyuth take to complete the ramaining job?
ഒരാൾ 20 ദിവസംകൊണ്ട് ഒരു ജോലി ചെയ്തുതീർക്കും. 12 ദിവസംകൊണ്ട് ആ ജോലിയുടെ എത്ര ശതമാനം തീർക്കും?
A and B can fill a tank in 9 hrs and 12 hrs respectively. But C can empty in 18 hours. Pipes A, B & C start at 3 pm, 4 pm and 5 pm respectively. At what time will the tank be filled?