  1. is a general timetable of manufacturing
  2. is the time phase of loading
  3. is loading all the work in process on machines according to their capacity

    A1, 3

    BNone of these

    CAll of these

    D2 only

    Answer:

    C. All of these

    Read Explanation:

    Scheduling involves preparing machine loads and fixing start and completion dates for each operation. Machines must be loaded based on their capability and capacity, and coordination with the sales department is necessary for delivery schedules