Rajeshwar can do a piece of work in 12 days, Vikram in 6 days and Tiger in 15 days. They all start the work together, but Rajeshwar leaves after 2 days and Vikram leaves 3 days before the work is completed. In how many days is the work completed?

A5 3/7

B5 4/7

C5 5/7

D5 6/7

Answer:

C. 5 5/7

Read Explanation:

Let the total work = LCM of (12, 6, 15) = 60 units

Daily work rates

  • Rajeshwar: (60/12 = 5) units/day

  • Vikram: (60/6 = 10) units/day

  • Tiger: (60/15 = 4) units/day


Work done in different periods

First 2 days (all three work):
(5+10+4)×2=19×2=38 units(5 + 10 + 4) \times 2 = 19 \times 2 = 38 \text{ units}

Last 3 days (only Tiger works):
4×3=12 units4 \times 3 = 12 \text{ units}

Let the total time = x days

So, the middle period (after Rajeshwar leaves and before Vikram leaves) is:
x−5 daysx - 5 \text{ days}
Duringthistime,<b>Vikram+Tiger</b>work:During this time, <b>Vikram + Tiger</b> work:
(10+4)(x−5)=14(x−5)(10 + 4)(x - 5) = 14(x - 5)


Total work equation

38+14(x−5)+12=6038 + 14(x - 5) + 12 = 60
38+14x−70+12=6038 + 14x - 70 + 12 = 60
14x−20=6014x - 20 = 60
14x=8014x = 80
x=8014=407x = \frac{80}{14} = \frac{40}{7}
]

The work is completed in 5575\frac{5}{7}


Related Questions:

A can do a piece of work in 12 days. B can do it in 18 days. With the assistance of C, they completed the work in 4 days. C alone can do it in ______________days.
A fort had provision of food for 150 men for 85 days. After 15 days, 25 men left the fort. Find the number of days for which the remaining food will last.
Ravi can complete one-fourth of the total work in 15 days, Chavi can complete one-third of the total work in 18 days, Dhani can complete half of the total work in 24 days. In how much time can Ravi, Chavi and Dhani complete three-fourth of the work together?
60 ആളുകൾ 10 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 6 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര ആളുകൾ അധികം വേണ്ടിവരും ?
A and B can complete a task in 12 days and 18 days, respectively. They begin the work together, but B leaves after 4 days. How many more days will A take to finish the remaining work?