A can do a piece of work in 12 days. B can do it in 18 days. With the assistance of C, they completed the work in 4 days. C alone can do it in ______________days.

A11

B8

C10

D9

Answer:

D. 9

Read Explanation:

9


Related Questions:

എ ബി സി എന്നിവയ്ക്ക് യഥാക്രമം 20 30 60 ദിവസങ്ങളിൽ ഒരു ജോലി ചെയ്യാൻ കഴിയും ഓരോ മൂന്നാം ദിവസവും ബി ,സി എന്നിവർ സഹായിച്ചാൽ എ ക്ക് എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കാൻ കഴിയും
P can do a piece of work in 48 days, which Q can do in 18 days. Q worked at it for 15 days. P can finish the remaining work in:
Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
Abhishek and Deepanshi undertake to do a piece of work for ₹1,000. Abhishek alone can do it in 5 days and Deepanshi alone can do it in 10 days. With the help of Chitransh, they finish it in 2 days. How much should Chitransh be paid for his contribution?
A 100-litre solution contains acid and water in the ratio 3:2. Some quantity of this solution is removed and replaced with pure acid. If the final ratio of acid to water becomes 7:3, how many litres of solution were replaced?