Rishi can do a piece of work in 8 hours. Shan can do it in 12 hours. With the assistance of Veer, they completed the work in 3 hours. In how many hours can Veer alone do it?

A8

B9

C7

D10

Answer:

A. 8

Read Explanation:

8


Related Questions:

If 200 men can dig a canal working for 8 hours a day in 6 days, how long will it take to dig the canal, if 300 men work 6 hours per day?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank if the capacity of each bucket is 9 litres?
15 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തുതീർക്കുന്ന ജോലി 10 ആളുകൾക്ക് ചെയ്തുതീർക്കാൻ എത്ര ദിവസം വേണം?
A, B and C can do a piece of work in 12 days, 14 days and 16 days respectively. All three of them started the work together and after working for four days C leaves the job, B left the job 4 days before completion of the work. Find the approximate time required to complete the work. (in days)
Isha can do a certain piece of work in 20 days. Isha and Smriti can together do the same work in 16 days, and Isha, Smriti and Ashlesha can do the same work together in 8 days. In how many days can Isha and Ashlesha do the same work?