Rishi can do a piece of work in 8 hours. Shan can do it in 12 hours. With the assistance of Veer, they completed the work in 3 hours. In how many hours can Veer alone do it?

A8

B9

C7

D10

Answer:

A. 8

Read Explanation:

Veer alone can complete the work in 8 hours.

To make this easy to solve without fractions, let’s find a total amount of work using the LCM (Least Common Multiple) of the given hours (8, 12, and 3).

  • Let the Total Work = 24 units (LCM of 8, 12, and 3).

Step 1: Find the work done by each per hour (Efficiency)

  • Rishi's efficiency: 24 units / 8 hours = 3 units/hour

  • Shan's efficiency: 24 units / 12 hours = 2 units/hour

  • Combined efficiency (Rishi + Shan + Veer): 24 units / 3 hours = 8 units/hour

Step 2: Find Veer's efficiency

  • Rishi and Shan together do: 3 + 2 =5 units/hour

  • Veer's work per hour = Combined efficiency - (Rishi + Shan)

  • Veer's efficiency = 8 - 5 = 3units/hour

Step 3: Calculate the time taken by Veer alone

  • Time = Total Work / Veer's Efficiency

  • Time = 24 / 3 = 8 hours


Related Questions:

32 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കുവാൻ 15 ദിവസം വേണമെങ്കിൽ 10 ദിവസം കൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കുവാൻ എത്ര ആളുകൾ വേണം ?
രാമു ഒരു ജോലി 6 ദിവസം കൊണ്ടും രാജു അതേ ജോലി 18 ദിവസം കൊണ്ടും ചെയ്യും. രണ്ടുപേരുംചേർന്നു ജോലി ചെയ്താൽ മുഴുമിക്കാൻ എത്ര ദിവസം വേണം?
A and B alone can complete a piece of work in 9 days and 12 days, respectively. In how many days will the work be completed if they work on alternate days starting with A?
image.png
Prakash and Vinesh can complete a certain piece of work in 10 and 8 days, respectively, They started to work together, and after 3 days, Vinesh left. In how many days will Prakash complete the remaining work?