A and B alone can complete a piece of work in 9 days and 12 days, respectively. In how many days will the work be completed if they work on alternate days starting with A?

A5135\frac13

B111311\frac13

C105610\frac56

D101410\frac14

Answer:

101410\frac14

Read Explanation:

A alone 9 days

B alone 12 days

total work is the LCM of 9 and 12 = 36

one day work of A is 36/9=4

one day work of B is 36/12=3

for alternate work starting A is

4,3,4,3,4,3,4,3,4,3...

after 10 days total work should be 35 work

next day will be A . one day work of A is 4 for one work it is 1/4 days

so the total work days is

101410\frac14


Related Questions:

Pipes A and B can fill a tank in 18 minutes and 27 minutes, respectively. C is an outlet pipe. When A, B and C are opened together, the empty tank is completely filled in 54 minutes. Pipe C alone can empty the full tank in:
A pipe can filla tankin 30 minutes. Due to a leak in the bottom it is filled in 40 minutes. If the tank is full, how much time will the leak take to empty it?
ഒരു കമ്പ്യൂട്ടർ ഗെയിമിൽ, ഒരു ബിൽഡറിന് 20 മണിക്കൂറിനുള്ളിൽ ഒരു മതിൽ നിർമ്മിക്കാൻ കഴിയും, ഒരു ഡിസ്ട്രോയറിന് 40 മണിക്കൂറിനുള്ളിൽ അത്തരമൊരു മതിൽ പൂർണ്ണമായും തകർക്കാൻ കഴിയും. തുടക്കത്തിൽ, ബിൽഡറും ഡിസ്ട്രോയറും ഒരു അടിസ്ഥാന തലത്തിൽ ഒരുമിച്ച് പ്രവർത്തിക്കാൻ തയ്യാറായിരുന്നു. എന്നാൽ 30 മണിക്കൂറിന് ശേഷം ഡിസ്ട്രോയർ പിൻവലിച്ചു. മതിൽ പണിയാൻ എടുത്ത മൊത്തം സമയം എത്രയാണ്?
Kartik can do a piece of work in 4 hours. Ishan can do it in 20 hours. With the assistance of Krish, they completed the work in 2 hours. In how many hours can Krish alone do it?
A,B യുടെ ഇരട്ടി വേഗത്തിൽ ജോലി ചെയ്യും. B 36 ദിവസം കൊണ്ട് ജോലി ചെയ്തു തീർക്കും എങ്കിൽ രണ്ടു പേരും കൂടി എത്ര ദിവസം കൊണ്ട് ആ ജോലി ചെയ്തു തീർക്കും?