The first and last activities of a network diagram

Acan always be eliminated

Bare always on the critical path

Calways have the maximum duration

Dalways have the minimum duration

Answer:

B. are always on the critical path

Read Explanation:

The first and last activities of a network diagram are always on the critical path, which is the sequential activities the critical path activities will lead to project deliverables delay. The critical path method identifies the critical activities that directly impact the project completion date.


Related Questions:

Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

  1. PERT is event-oriented while CPM is activity-oriented.
  2. PERT is probabilistic while CPM is deterministic.
  3. Levelling and smoothing are the techniques related to resource scheduling in CPM.
    When total supply is equal to the total demand for a transportation problem, it is termed as a/an _____________ transportation problem.
    Which of the following artificial activity suggests that an activity following it cannot happen unless, the previous activity is completed?
    In the Simplex method if in pivot column all the entries are negative or zero when choosing leaving variable then
    The parameters assumed in a Linear programming model are treated as