Let number of days taken by B = x
Then:
Given: A takes 12 days
2x=12⇒x=6
So:
A = 12 days → work/day = ( \frac{1}{12} )
B = 6 days → work/day = ( \frac{1}{6} )
C = 3 days → work/day = ( \frac{1}{3} )
Work done in 3-day cycle (B, A, C):
61+121+31
LCM = 12:
=122+1+4=127
After 3 days → work done = (127)
Remaining work:
1−127=125
Day 4 (B works):
125−61=125−122=123=41
Day 5 (A works):
41−121=123−121=122=61
Day 6 (C works):
61−31⇒work finishes
C completes the remaining work in:
3161=21 day
Total time:
5+21=5.5 days