Which of the following distribution represents the time estimates in PERT ?

APoisson distribution

BNormal distribution

CBeta distribution

DWeibull distribution

Answer:

C. Beta distribution

Read Explanation:

PERT estimates use Beta distribution to calculate expected duration of an activity. It considers optimistic, most likely and pessimistic time. Poisson distribution predicts the probability of certain events happening.


Related Questions:

A point which represents either starting or termination of activity is known as -
The first and last activities of a network diagram
In a network diagram, an activity having a dotted arrow between activities is often referred to as a/an __________________ activity.
A variable that has no physical meaning, but is used to obtain an initial basic feasible solution to the linear programming problem is referred to as:
________________is an operation research technique which aids the manager in making decisions involving the establishment of service facilities to meet irregular demands.