Which of the following is NOT correct critical path method (CPM) used in Project scheduling?
AThe path with the longest time sequence the critical path.
BFor each activity earliest start time and latest start time are computed.
CThe length of the critical path determines the minimum time in which the entire project can be completed.
DThe path with the shortest time sequence is the critical path.