Challenger App

No.1 PSC Learning App

1M+ Downloads
Which of the following is NOT correct critical path method (CPM) used in Project scheduling?

AThe path with the longest time sequence the critical path.

BFor each activity earliest start time and latest start time are computed.

CThe length of the critical path determines the minimum time in which the entire project can be completed.

DThe path with the shortest time sequence is the critical path.

Answer:

D. The path with the shortest time sequence is the critical path.

Read Explanation:

The critical path method (CPM) is used to identify tasks necessary for project completion and determine scheduling flexibilities. The longest sequence of activities that must be finished on time in order for the entire project to be complete is the critical path. PERT is a method used to examine tasks and determine a CPM variation. PERT is event-oriented, associated with probabilistic activities, and based on a three- time estimate to complete an activity. CPM is activity- oriented, associated with deterministic activities.


Related Questions:

In a transportation problem North-West corner rule would yield :

Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

  1. PERT is event-oriented while CPM is activity-oriented.
  2. PERT is probabilistic while CPM is deterministic.
  3. Levelling and smoothing are the techniques related to resource scheduling in CPM.
    While doing the project planning of a Construction: project, using PERT, it is intended to identify the variance of the project. This can be done by:
    While solving a linear programming model, if a redundant constraint is added, then what will be its effect on existing solution?
    Which of the following location analysis techniques involves a method of evaluating different locations based on the load being transported and the distance?