Which structure involves employees reporting to both functional managers and project managers, promoting cross-functionality?

ALine Structure

BCommittee Structure

CMatrix Structure

DProject Structure

Answer:

C. Matrix Structure

Read Explanation:

  • Matrix Structure facilitates dual authority—employees report to both functional and project managers—enhancing flexibility but risking confusion and conflict


Related Questions:

Consider the following statements regarding Activities of an Industrial Undertaking by Fayol:

I. Fayol divided activities into six groups: technical (production, manufacture), commercial (buying, selling), financial (capital search and optimum use).

II. Other groups include security (property and personnel protection), accounting (stock-taking, balance sheet, costs, statistics).

III. Managerial activities (planning, organization, command, coordination, control) are excluded from Fayol's classification.

Which among the following advocates centralization and hierarchy, but also stresses that leadership should balance equity and esprit de corps?

David Easton’s premises for Behaviouralism emphasize:

I. Verification, requiring knowledge acceptance only if it can be empirically tested.

II. Systematisation, viewing research and theory-building as mutually exclusive endeavors.

III. Values, demanding that empirical explanation must inherently carry ethical judgments.

Which of the following is correct?

According to the foundational statements on Principles of Administration, what role do principles serve in the management process?

Assertion (A): Classical theory treats administration as a universal science applicable across all organizational contexts.

Reason (R): Fayol's principles, such as centralization, are flexible and adaptable to varying conditions, ensuring positivism and universalism.