Challenger App

No.1 PSC Learning App

1M+ Downloads
X can complete a task in 15 days, and Y can complete the same task in 20 days. If X and Y work on alternate days starting with X, in how many days will the work be completed?

A17

B22

C15

D19

Answer:

A. 17

Read Explanation:

We are given:

  • X’s 1-day work = ( \frac{1}{15} )

  • Y’s 1-day work = ( \frac{1}{20} )

  • They work alternately starting with X

    Work in 2 days (X + Y)

115+120\frac{1}{15} + \frac{1}{20}

LCM = 60:

=460+360=760= \frac{4}{60} + \frac{3}{60} = \frac{7}{60}

So in 2 days → work done = 7/60

Find full cycles needed

We need 1 full work:

After 8 such cycles (16 days):
8×760=5660=14158 \times \frac{7}{60} = \frac{56}{60} = \frac{14}{15}

Remaining work:
11415=1151 - \frac{14}{15} = \frac{1}{15}

Next day is X’s turn

X does:
115\frac{1}{15}

So remaining work completes exactly in next day

Total days

  • 16 days + 1 day = 17 days

    Final Answer: 17 days


Related Questions:

18 പേർ 28 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 24 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ എത ജോലിക്കാർ വേണം?
A യും B യും C യും കൂടി ഒരു ജോലി 4 ദിവസം കൊണ്ടു ചെയ്തുതീർക്കുന്നു. A തനിയെ 12 ദിവസം കൊണ്ടും B തനിയെ 18 ദിവസം കൊണ്ടും ചെയ്തുതീർത്താൽ C യ്ക്ക് തനിയെ ആ ജോലി ചെയ്യാൻ വേണ്ടി വരുന്ന ദിവസമെത്ര?
A and B share a rented field. A utilizes 20 horses for 5 months, while B uses 30 cows for 4 months and 45 sheep for 5 months. If 2 horses are equivalent to 5 cows, and 3 cows are equal to 9 sheep. What portion of the rent is A pay ?
'A' യും 'B' യും കൂടി 18 ദിവസങ്ങൾ കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി 'B' യും 'C' യും കൂടി 24 ദിവസങ്ങൾ കൊണ്ടും 'A' യും 'C' യും കൂടി 36 ദിവസങ്ങൾ കൊണ്ടുംതീർക്കും. എങ്കിൽ, 'C' ഒറ്റയ്ക്ക് ഈ ജോലി തീർക്കാൻ എത്ര ദിവസങ്ങൾ എടുക്കും?
Anjali can do a certain piece of work in 16 days. Anjali and Ayushi can together do the same work in 10 days, and Anjali, Ayushi and Ankita can do the same work together in 8 days. In how many days can Anjali and Ankita do the same work?