A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?

A20 men

B30 men

C40 men

D50 men

Answer:

C. 40 men

Read Explanation:

X×60=50(x+8)X\times{60}=50(x+8)

X=(50×8)(6050)X=\frac{(50\times{8})}{(60-50)}

=40010=40men=\frac{400}{10}=40 men


Related Questions:

ജോണും ദീപുവും ചേർന്ന് ഒരു ജോലി ചെയ്തു തീർക്കാൻ 45 ദിവസം എടുക്കുന്നു.എന്നാൽ ജോൺ ഒറ്റയ്ക്ക് ഈ ജോലി 70 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ദീപു ഒറ്റയ്ക്ക്ഇതേ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും?
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
A, B and C complete a piece of work in 20, 9 and 12 days respectively. Working together, they will complete the same work in
C alone can complete a work in 20 days and D alone can complete the same work in 30 days. In how many days C and D together can complete the same work?
A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 12 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is: