For plastering with cement mortar 1:5, 12 mm thick one coat, the quantity of cement for 10 m²
The unit of quantity of shutters of door and window is calculated in
The size of a room is 5 m x 3 m, thickness of wall 20 cm and a slab projection of 30 cm from walls. If the thickness of slab is 100 mm,the quantity of cement concrete required for room slab
When small items, are estimated, for which detailed quantities cannot be taken out,they are considered as
The unit of measurement, for reinforced cement concrete, work is
The unit of measurement, for 'pointing of stone masonry' work is
Quantity of cement required for 1 m of cement concrete mix 1:2:4
Unit of wood work planed and framed for frames of doors and windows
Quantity of water required per 50 kg of cement, for M20 concrete mix
While estimating the area of wall plastering deduction is made for both sides openings, when the area of the opening is
Quantity of cement required for one cubicmeter R.R.M. in 1:8 cement mortar
For plastering with cement mortar 1:4, 12mm thick one coat, the cement required for10 m² is
The item of wood work which is measured in cu. m is:
The estimated quantity of cement required in cement mortar(1:6) per cubic metre will be
All the work executed shall be measured and entered in a permanent record called
The expected out turn of half brick partition wall per mason per day is:
Quantity of dry sand required for plastering 100 m² brick wall, 12mm, plastering thickness:
Unit of wood work panelled and framed for frames of doors and windows