Latest finish time in CPM technique is indicated by a:
The capacity of doing work by a skilled labour, is the form of quantity of work per day is known as:
The damp proof course is measured in:
The sanction of the detailed estimate, design calculations, quantities of works, rates and cost of the work by the competent authority of the engineering department is called:
Which department looks after the execution and maintenance of water supply and sanitary works?
The time by which a particular activity may be delayed without affecting the preceeding and succeeding activities is known as:
Work costing less than 20,000 is called:
The head of the division of public works department is
The most reliable estimate is :
PERT stand for:
In PERT technique, completion of an activity is called:
The item of wood work which is measured in cu. m is:
The most reliable estimate is:
PERT analysis is based on:
When the expenditure on a work exceeds or is likely to exceed the amount of administrative sanction by more than 10%,
Barbed wire fencing units of measurement in MKS
Life period of a building should be at least .......................years
Area of the horizontal circulation may constitute about ........................of the total plan area of a residential building
As per National Building Code, the minimum area for a kitchen in residential building is
The estimated quantity of cement required in cement mortar(1:6) per cubic metre will be
While submitting tender the contractor is to deposit 2% of estimated cost as
All the work executed shall be measured and entered in a permanent record called
For compacting the quantity of earthwork using prismoidal formula the number of required sectional area
In an estimate a certain amount in the form of contingencies of ...........................% to ............................% of estimate cost.
Work-charged establishment a percentage of ............................ to............................ of the estimated cost is included in the estimated.
For calculating quantity of steel density of steel may betaken as:
It is the value at the end of utility period without being dismantled:
The essential requirements to prepare good estimate are:
Activity having negative float is called:
The time corresponding to minimum total project cost is:
Which of the following is an activity?
The expected out turn of half brick partition wall per mason per day is:
The amount charged by the engineering department to meet the expense of designing, planning, supervision etc for a work of other department is called:
The rate of payment for supply of sand is per
The item of steel which is measured in sq. m is
The accident cost analysis is estimated by conducting......................................
The value at the end of the utility period
Pick up the correct statement from the following
The owner is an absolute legal possession of property:
A fund which is accumulated gradually by deposits for replacement of any construction at the end of its useful life is known as
Quantity of dry sand required for plastering 100 m² brick wall, 12mm, plastering thickness:
In the specifications of earthwork, initial lead is specified as:
Percentage of contingencies added to get the total cost of a project?
The original cost of property minus depreciation is
The Incidental expense of a miscellaneous character which cannot be reasonably predicted during preparation of the estimate is indicated by the term:
Which of the following data is necessary for making an estimate?
The estimating, for plastering usually no deduction is made for:
The Instrument which register the number of paces of the person carrying it: