Challenger App

No.1 PSC Learning App

1M+ Downloads
24 people can finish a job by 10 days. How many days will be required to finish the same job by 8 people?

A20

B26

C30

D32

Answer:

C. 30

Read Explanation:

(24 x 10)/8 = 30


Related Questions:

51 men can complete a work in 12 days. Four days after they started working 6 more men joined them. How many days will they now take to complete the remaining work?
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:
ഒരു പുരുഷനും സ്ത്രീക്കും അവർ ഒരുമിച്ച് ചെയ്ത ജോലികൾക്ക് 20 ദിവസത്തേക്ക് 1500 രൂപ വേതനം ലഭിച്ചു. പുരുഷന്റെ കാര്യക്ഷമത സ്ത്രീയുടേതിനേക്കാൾ ഇരട്ടിയാണെങ്കിൽ, സ്ത്രീയുടെ ദൈനംദിന വേതനം കണ്ടെത്തുക?