App Logo

No.1 PSC Learning App

1M+ Downloads
60 men can complete a work in 40 days. They start work together but after every 10 day, 5 men leave the work. In how many days will the work be completed?

A47.5

B49.5

C42.5

D45.5

Answer:

A. 47.5

Read Explanation:

Total workload = 60 × 40 = 2400 60 men did the work in 10 days = 600 55 men did the work in 10 days = 550 50 men did the work in 10 days = 500 45 men did the work in 10 days = 450 Total work units left = 2400 – (600 + 550 + 500 + 450) = 2400 – 2100 = 300 40 men will do 300 units in = 300/40 = 7.5 Total number of days to finish the work = 40 + 7.5 = 47.5 days


Related Questions:

A യ്ക്ക് 5 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും B 6 ദിവസം കൊണ്ട് ഇതേ ജോലി പൂർത്തിയാക്കുന്നു . രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
A and B together can complete a work in 30 day. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
E and F can do a work in 10 days. If E alone can do it in 30 days, F alone can do it in _____ days.
18 ആളുകള്‍ 36 ദിവസം കൊണ്ട് ചെയ്തു തീര്‍ക്കുന്ന ഒരു ജോലി 12 ആളുകള്‍ എത്ര ദിവസം കൊണ്ട് ചെയ്ത് തീര്‍ക്കും ?
15 പേർ 24 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 18 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര പേർ വേണം?