Challenger App

No.1 PSC Learning App

1M+ Downloads
60 men can complete a work in 40 days. They start work together but after every 10 day, 5 men leave the work. In how many days will the work be completed?

A47.5

B49.5

C42.5

D45.5

Answer:

A. 47.5

Read Explanation:

Total workload = 60 × 40 = 2400 60 men did the work in 10 days = 600 55 men did the work in 10 days = 550 50 men did the work in 10 days = 500 45 men did the work in 10 days = 450 Total work units left = 2400 – (600 + 550 + 500 + 450) = 2400 – 2100 = 300 40 men will do 300 units in = 300/40 = 7.5 Total number of days to finish the work = 40 + 7.5 = 47.5 days


Related Questions:

10 പുരുഷന്മാർ ഒരു ജോലി 12 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ കഴിയുമെങ്കിൽ അതെ ജോലി ചെയ്യാൻ 12 പുരുഷന്മാർ എടുക്കുന്ന സമയം എത്ര?
Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?
A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count 450 eggs?
A ക്ക് ഒരു ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാനാകും, B, A യേക്കാൾ മൂന്ന് മടങ്ങ് വേഗത്തിൽ ജോലി ചെയ്യാൻ കഴിയും, A യേക്കാൾ അഞ്ച് മടങ്ങ് വേഗത്തിൽ ജോലി ചെയ്യാൻ C ക്ക് കഴിയും. ആ ജോലി അവർ ഒരുമിച്ച് ചെയ്യാൻ എത്ര ദിവസമെടുക്കും?