Challenger App

No.1 PSC Learning App

1M+ Downloads
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?

A8

B10

C7

D9

Answer:

B. 10

Read Explanation:

8 men = 10 women ie, 5 women = 4 men 28 men + 15 women = 28 men + 12men = 40 men 8 men can do a piece of work in 50 days 1 men can do the same work in (50 × 8) days Then 40 men can do the same work in (50 × 8)/40 = 10 days


Related Questions:

A can finish painting a sari in 11 days, B in 20 days and C in 55 days, if they work independently. In how many days can the work be completed if A is assisted by B on every odd numbered day and by C on every even numbered day till the work completes?
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it ?
A, B and C can do a piece of work in 12 days, 14 days and 16 days respectively. All three of them started the work together and after working for four days C leaves the job, B left the job 4 days before completion of the work. Find the approximate time required to complete the work. (in days)
A can finish 3/5th of a task in 6 days and B can finish 2/3th of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. B and C, working together, will complete the same task in:
രണ്ട് പൈപ്പുകൾക്ക് യഥാക്രമം 12 മണിക്കൂറും 15 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും 4 മണിക്കൂർ തുറന്നു ആദ്യത്തെ പൈപ്പ് അടച്ചാൽ, ശേഷിക്കുന്ന ടാങ്ക് നിറയ്ക്കാൻ രണ്ടാമത്തെ പൈപ്പ് എടുക്കുന്ന സമയം കണ്ടെത്തുക