9 men and 12 women can complete a work in 4 days, whereas 3 men and 6 women can complete it in 10 days. The number of days in which 15 women will complete the work is:

A9

B10

C8

D12

Answer:

C. 8

Read Explanation:

Solution: Given: 9 men and 12 women can complete a work in 4 days 3 men and 6 women can complete it in 10 days. Calculation: According to question Work done is same, so, (9 men + 12 women) × 4 = (3 men + 6 women) × 10 ⇒ 36 men - 30 men = 60 women - 48 women ⇒ 6 men = 12 women ⇒ 1 man = 2 women As 9 men and 12 women can complete a work in 4 days 9 men and 12 women = 18 women + 12 women = 30 women Time taken by 30 women to do the work = 4 days Time taken by 1 woman = (4 × 30) days = 120 days ∴ Time taken by 15 woman = (120/15) days = 8 days


Related Questions:

Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?
Two pipes A and B can fill a tank in 15 hours and 20 hours, respectively, while a third pipe C can empty the full tank in 30 hours. If all the three pipes operate simultaneously, in how much time will the tank, initially empty, be filled?
4 ടാപ്പുകൾക്ക് 10 മണിക്കൂർ കൊണ്ട് ഒരു ടാങ്ക് നിറക്കാൻ കഴിയും. അപ്പോൾ 6 ടാപ്പുകൾക്ക് ഇതേ ടാങ്കിൽ എത്ര മണിക്കൂർ കൊണ്ട് നിറയ്ക്കാനാകും?
Efficiency of A is twice more than that of B. If B takes 28 days more to finish a work, In how many days; (A + B) will complete the whole work?