App Logo

No.1 PSC Learning App

1M+ Downloads
A and B undertake to complete a piece of work for ₹600. A alone can complete it in 4 days while B alone can complete it in 6 days. With the help of C, they finish the work in 2 days. Find the share of C in the payment received.

A200

B78

C100

D300

Answer:

C. 100

Read Explanation:

A alone complete a work =4 days B alone complete a work =6 days LCM of these two is the work ie =12 efficiency of A=12/4=3 efficiency of B = 12/6=2 A and B are work together the one day work is 5 if C is included the work they will complete the work in 2 days so the efficiency of C is 2 days=12/efficiency of (A+B+C) 2=12/(5+C) 1=6/(5+C) (5+C)=6 C=1 so the ratio of efficiency of A:B:C = 3:2:1 the share of C=600*(1/6)=100


Related Questions:

A and B can separately do a piece of work in 6 days and 12 days respectively. How long will they together take to do the work ?
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
The efficiency of A, B, and C is 2 : 3 : 5. A alone can complete a work in 50 days. They all work together for 5 days and then C left the work, in how many days A and B together can complete the remaining work?
8 men and 12 women finish a job in 4 days. While 6 men and 14 women in 5 days. In how many days will 20 women finish the job?
ജോണിക്ക് 40 ദിവസം കൊണ്ടും രാജുവിന് 48 ദിവസം കൊണ്ടും ബോബിക്ക് 60 ദിവസം കൊണ്ടും ഒരു ജോലി തീർക്കാൻ കഴിയും. അവർ 4 ദിവസം ഒരുമിച്ച് ജോലി ചെയ്തു. തുടർന്ന് രാജു പോയി. അതിനുശേഷം ജോണിയും ബോബിയും 12 ദിവസം ഒരുമിച്ച് ജോലി ചെയ്ത ശേഷം ജോണി പോയി. ബോബിയുടെ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസമെടുക്കും ?