App Logo

No.1 PSC Learning App

1M+ Downloads
A and B undertake to complete a piece of work for ₹600. A alone can complete it in 4 days while B alone can complete it in 6 days. With the help of C, they finish the work in 2 days. Find the share of C in the payment received.

A200

B78

C100

D300

Answer:

C. 100

Read Explanation:

A alone complete a work =4 days B alone complete a work =6 days LCM of these two is the work ie =12 efficiency of A=12/4=3 efficiency of B = 12/6=2 A and B are work together the one day work is 5 if C is included the work they will complete the work in 2 days so the efficiency of C is 2 days=12/efficiency of (A+B+C) 2=12/(5+C) 1=6/(5+C) (5+C)=6 C=1 so the ratio of efficiency of A:B:C = 3:2:1 the share of C=600*(1/6)=100


Related Questions:

A ക്ക് ഒരു ജോലി 6 ദിവസം കൊണ്ടും B ക്ക് 4 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
15 men can complete a task in 10 days. In how many days can 20 men complete the same task?5.5 days
A എന്ന് പൈപ്പ് തുറന്നാൽ ടാങ്ക് നിറയാൻ 10 മിനിറ്റ് വേണം. B എന്ന പൈപ്പ് തുറന്നാൽ നിറഞ്ഞിരിക്കുന്ന ടാങ്ക് 15 മിനിറ്റ് കൊണ്ട് കാലിയാകും. എന്നാൽ രണ്ട് പൈപ്പും ഒരുമിച്ചു തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും?
A, B എന്നീ രണ്ട് പ്രിന്റിംഗ് മെഷീനുകൾക്ക് 5 മണിക്കൂറിനുള്ളിൽ 2400 പേജുകൾ 5 ദിവസത്തിനുള്ളിൽ അച്ചടിക്കാൻ കഴിയും. മെഷീൻ A യ്ക്ക് 2.5 മണിക്കൂർ കൊണ്ട് എത്ര പേജുകൾ അച്ചടിക്കാൻ കഴിയുമോ, അത്രയും പേജുകൾ മെഷീൻ B യ്ക്ക് 1.5 മണിക്കൂറിനുള്ളിൽ അച്ചടിക്കാൻ കഴിയും.1 മണിക്കൂറിനുള്ളിൽ മെഷീൻ B യ്ക്ക് എത്ര പേജുകൾ അച്ചടിക്കാൻ കഴിയും?
A യും B യും ചേർന്ന് 20 ദിവസം കൊണ്ട് ഒരു പ്രവൃത്തി ചെയ്യാൻ കഴിയും. അവർ ഒരുമിച്ച് പ്രവൃത്തി ആരംഭിക്കുന്നു, പക്ഷേ പ്രവൃത്തി പൂർത്തിയാകുന്നതിന് 5 ദിവസം മുമ്പ് A യ്ക്ക് വിട്ടുപോകേണ്ടി വരുന്നു. ബാക്കിയുള്ള പ്രവൃത്തി 18 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ B യ്ക്ക് കഴിയുമെങ്കിൽ, B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് മുഴുവൻ പ്രവൃത്തിയും പൂർത്തിയാക്കും?