Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.

A8 days

B7 2/3 days

C7 days

D6 days

Answer:

A. 8 days

Read Explanation:

Let the required days be x A work for (x-2) days, while 'B' work for 'x' days According to the question, (x - 2)/10 + x/20 = 1 2x - 4 +x = 20 3x =24 x = 8 days


Related Questions:

A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?
രാജൻ ഒരു ജോലി ചെയ്തു തീർക്കാൻ 10 ദിവസവും, ജോണി അതേ ജോലി ചെയ്തു തീർക്കാൻ 15 ദിവസവും എടുക്കും. എങ്കിൽ രണ്ടാളും ഒരുമിച്ച് ആ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും ?

Pipes A and B can fill a tank in 12 h and 18 h, respectively, whereas pipe C can empty the full tank in 8 h. A and B opened for 4124\frac{1}{2} h and then closed. C alone will empty the tank in (in h):

A and B together can do a certain work in x days. Working alone, A and B can do the same work in (x + 8) and (x + 18) days, respectively. A and B together will complete 5/6 of the same work in:
ഒരു ടാങ്കിൻറ നിർഗമന കുഴൽ തുറന്നാൽ 2 മണിക്കൂർ കൊണ്ട് നിറയും. ബഹിർഗമന കുഴൽ തുറന്നാൽ 3 മണിക്കൂർ കൊണ്ട് ടാങ്ക് കാലിയാവും. രണ്ട് കുഴലുകളും ഒരുമിച്ച് തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും?