Consider the following statements regarding project management:Which of the given statements are INCORRECT?
- PERT is probabilistic and CPM is deterministic.
- In PERT, network slack on various events is calculated,
- In PERT, activity duration is normally distributed and project duration is beta distributed.
- The critical path of a network is the path that takes the shortest time.
AAll
B3 only
C3, 4
D2, 3