How many men will be required to plough 50 acres of land in 10 days if 15 men are required 6 days to plough 10 acres of land?

A45

B40

C55

D50

Answer:

A. 45

Read Explanation:

Solution: Given: 15 men required 6 days to plough 10 acres of land Formula Used: M­1D1/W1 = M­2D2/W2 Calculation: ⇒ M­1 = 15, D1 = 6, W1 = 10 ⇒ M­2 =? ,D2 = 10, W2= 50 ⇒ 15 × 6/10 = M2 × 10/50 ⇒ M2 = 45 ∴ The total men required is 45


Related Questions:

A pipe can fill the tank in 10 minutes and another pipe can empty it in 12 minutes. If both the pipes are opened the time in which the tank is filled
A and B together can work in 6 days. A alone 8 days. In how many days B alone do it?
Pipes A and B can fill a tank in 18 minutes and 27 minutes, respectively. C is an outlet pipe. When A, B and C are opened together, the empty tank is completely filled in 54 minutes. Pipe C alone can empty the full tank in:
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
A bicycle is sold at a profit of 10%. Had it been sold for 900 less, there would have been a loss of 10%. The cost price of the bicycle is: