The working efficiency of Raja, Ram and Mohan is 6 : 3 : 2. Raja can complete the whole work in 10 days. Raja and Ram together work for the first two days and then Raja and Mohan work for next 4 days and the remaining work is completed by Mohan. Find the total time taken to complete the work.