In network techniques, PERT stands for:

AProgramme Evaluation and Review Technique.

BProject Evaluation and Review Technique.

CProcess Evaluation and Review Technique.

DProduction Evaluation and Review Technique.

Answer:

A. Programme Evaluation and Review Technique.

Read Explanation:

PERT (Programme Evaluation and Review Technique) a network technique used in project management to estimate activity duration. It uses three cases - most optimistic, most pessimistic, and most likely durations - to determine the probability for each duration. PERT assumes a Beta distribution for the activity times, unlike CPM which considers the most likely duration. PERT was developed to address the needs of projects being done for the first time.


Related Questions:

Which of the following statement/statements is/are correct?
Positive slack in PERT indicates
Any network must have flow between sources and sink equal to capacity of:
In Northwest corner method the allocations are made
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-