Puneet alone can complete a work in 30 days and Sumit alone can complete the same work in half the time taken by Puneet. In how many days will both of them together complete 1/2 of the total work?

A7 days

B10 days

C5 days

D9 days

Answer:

C. 5 days

Read Explanation:

Solution: Given: Time taken by Puneet to complete the work = 30 days Time taken by Sumit to complete the work = 30/2 = 15 days Concept Used: Total Work = Efficiency × Time Calculation: Let the total work be 30 units (LCM of 30 & 15) ⇒ Efficiency of Puneet = 30 ÷ 30 = 1 unit ⇒ Efficiency of Sumit = 30 ÷ 15 = 2 units Efficiency of Puneet & Sumit = 1 + 2 = 3 units Time required by Puneet & Sumit to complete half work ⇒ (30/2) ÷ 3 = 15 ÷ 3 = 5 days ∴ Puneet & Sumit can complete half of the total work in 5 days.


Related Questions:

Two pipes can fill a tank in 30 hours and 40 hours, respectively. Find the time (in hours) taken to fill the tank when both the pipes are opened simultaneously.
Anu can type 40 pages of a book in 10 hours. Anu and Mohit together can type 270 pages in 54 hours. In what time (in hours) can Mohit alone type 20 pages?
16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?
A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 12 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is:
A 60 ദിവസം കൊണ്ടും B 40 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യുമെങ്കിൽ രണ്ടുപേരും ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ഈ ജോലി ചെയ്യും?