Challenger App

No.1 PSC Learning App

1M+ Downloads
Raju can complete a work in 20 days, which Bobby, Arjun and Habib can finish Independently in 27, 30 and 36 days respectively, Raju and Arjan starts doing this work jointly and continues on it for 4 days and stops working. If one of Habib and Hobby has to complete the work, how many more days they may take respectively?

A24, 18

B36, 27

C24, 20

D30, 25

Answer:

A. 24, 18

Read Explanation:

Work and Time Problems Explanation

  • Understanding Work and Time: This type of problem deals with the rate at which individuals or groups complete tasks. The fundamental concept is that Work = Rate × Time. The rate of work is the amount of work done per unit of time.

  • Calculating Individual Rates:

    • Raju's rate: If Raju completes the work in 20 days, his rate is 1/20 of the work per day.

    • Bobby's rate: If Bobby completes the work in 27 days, his rate is 1/27 of the work per day.

    • Arjun's rate: If Arjun completes the work in 30 days, his rate is 1/30 of the work per day.

    • Habib's rate: If Habib completes the work in 36 days, his rate is 1/36 of the work per day.

  • Joint Work Calculation:

    • Raju and Arjun work together for 4 days.

    • Their combined rate is Raju's rate + Arjun's rate = 1/20 + 1/30.

    • To add these fractions, find a common denominator (LCM of 20 and 30 is 60): (3/60) + (2/60) = 5/60 = 1/12 of the work per day.

    • Work done by Raju and Arjun in 4 days = Combined rate × Time = (1/12) × 4 = 4/12 = 1/3 of the total work.

  • Remaining Work:

    • Total work is considered as 1 unit.

    • Remaining work = Total work - Work done = 1 - 1/3 = 2/3 of the total work.

  • Calculating Time for Habib and Bobby:

    • Habib's remaining days: If Habib has to complete the remaining 2/3 work, the time taken would be Remaining Work / Habib's rate = (2/3) / (1/36).

    • To divide fractions, multiply by the reciprocal: (2/3) × 36 = 72/3 = 24 days.

    • Bobby's remaining days: If Bobby has to complete the remaining 2/3 work, the time taken would be Remaining Work / Bobby's rate = (2/3) / (1/27).

    • To divide fractions, multiply by the reciprocal: (2/3) × 27 = 54/3 = 18 days.


Related Questions:

ആരുഷും മഹിയും ചേർന്ന് 10 ദിവസം കൊണ്ട് ഒരു പണി ചെയ്യാം. ആരുഷിന് മാത്രം 15 ദിവസത്തിനുള്ളിൽ ഒരേ ജോലി ചെയ്യാൻ കഴിയുമെങ്കിൽ, മഹിക്ക് മാത്രം എത്ര ദിവസമെടുക്കും അതേ ജോലി ചെയ്യാൻ?
5 മുതിർന്നവർ ഒരു ജോലി 3 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും 3 കുട്ടികൾ ഇതേ ജോലി 5 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും 4 മുതിർന്നവരും 2 കുട്ടികളും ഈ ജോലി ചെയ്തു തീർക്കാൻ എടുക്കുന്ന സമയം എത്ര?
A ഒരു ജോലിയുടെ 1/2 ഭാഗം 5 ദിവസംകൊണ്ടും B അതേ ജോലിയുടെ 1/3 ഭാഗം 4 ദിവസം കൊണ്ടും പൂർത്തിയാക്കിയാൽ A യും B യും ഒരുമിച്ച് ആ ജോലി എത്ര ദിവസംകൊണ്ട് പൂർത്തിയാക്കും ?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank if the capacity of each bucket is 9 litres?
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?