Challenger App

No.1 PSC Learning App

1M+ Downloads
Raju can complete a work in 20 days, which Bobby, Arjun and Habib can finish Independently in 27, 30 and 36 days respectively, Raju and Arjan starts doing this work jointly and continues on it for 4 days and stops working. If one of Habib and Hobby has to complete the work, how many more days they may take respectively?

A24, 18

B36, 27

C24, 20

D30, 25

Answer:

A. 24, 18

Read Explanation:

Work and Time Problems Explanation

  • Understanding Work and Time: This type of problem deals with the rate at which individuals or groups complete tasks. The fundamental concept is that Work = Rate × Time. The rate of work is the amount of work done per unit of time.

  • Calculating Individual Rates:

    • Raju's rate: If Raju completes the work in 20 days, his rate is 1/20 of the work per day.

    • Bobby's rate: If Bobby completes the work in 27 days, his rate is 1/27 of the work per day.

    • Arjun's rate: If Arjun completes the work in 30 days, his rate is 1/30 of the work per day.

    • Habib's rate: If Habib completes the work in 36 days, his rate is 1/36 of the work per day.

  • Joint Work Calculation:

    • Raju and Arjun work together for 4 days.

    • Their combined rate is Raju's rate + Arjun's rate = 1/20 + 1/30.

    • To add these fractions, find a common denominator (LCM of 20 and 30 is 60): (3/60) + (2/60) = 5/60 = 1/12 of the work per day.

    • Work done by Raju and Arjun in 4 days = Combined rate × Time = (1/12) × 4 = 4/12 = 1/3 of the total work.

  • Remaining Work:

    • Total work is considered as 1 unit.

    • Remaining work = Total work - Work done = 1 - 1/3 = 2/3 of the total work.

  • Calculating Time for Habib and Bobby:

    • Habib's remaining days: If Habib has to complete the remaining 2/3 work, the time taken would be Remaining Work / Habib's rate = (2/3) / (1/36).

    • To divide fractions, multiply by the reciprocal: (2/3) × 36 = 72/3 = 24 days.

    • Bobby's remaining days: If Bobby has to complete the remaining 2/3 work, the time taken would be Remaining Work / Bobby's rate = (2/3) / (1/27).

    • To divide fractions, multiply by the reciprocal: (2/3) × 27 = 54/3 = 18 days.


Related Questions:

A juice vendor mixes water with pure orange juice. If he sells the mixture at the cost price of pure orange juice and makes a profit of 20%, what is the ratio of water to pure orange juice in the mixture, respectively?
A, B എന്നീ പൈപ്പുകൾ യഥാക്രമം 12 മണിക്കൂറും 15 മണിക്കുറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കും രണ്ട് പൈപ്പുകളും ഒരുമിച്ചു തുറന്നാൽ എത്ര മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയും?
A യും B യും ചേർന്ന് ഒരു ജോലി ഏഴു ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും . A യ്ക്ക് B യുടെ 1 3/4 മടങ്ങ് കാര്യക്ഷമതയുണ്ട് അതേ ജോലി A യ്ക്ക് മാത്രം എത്ര ദിവസം കൊണ്ട് ചെയ്യാൻ കഴിയും ?
A 100-litre solution contains acid and water in the ratio 3:2. Some quantity of this solution is removed and replaced with pure acid. If the final ratio of acid to water becomes 7:3, how many litres of solution were replaced?
സന്ധ്യ ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ഗോപു അതു ചെയ്യാൻ 60 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടു പേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?