Challenger App

No.1 PSC Learning App

1M+ Downloads
Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?

A22 days

B20 days

C24 days

D18 days

Answer:

C. 24 days

Read Explanation:

This is an inverse proportion problem. If you decrease the number of typists, it will take longer to complete the same amount of work.

Here's how to solve it:

  • Total work: 6 typists * 16 days = 96 "typist-days" (This represents the total amount of work to be done)

  • Days for 4 typists: 96 typist-days / 4 typists = 24 days

Therefore, 4 typists will take 24 days to complete the same work.


Related Questions:

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?
If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will B alone complete 20% of the remaining work?
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
A, B എന്നീ രണ്ട് പ്രിന്റിംഗ് മെഷീനുകൾക്ക് 5 മണിക്കൂറിനുള്ളിൽ 2400 പേജുകൾ 5 ദിവസത്തിനുള്ളിൽ അച്ചടിക്കാൻ കഴിയും. മെഷീൻ A യ്ക്ക് 2.5 മണിക്കൂർ കൊണ്ട് എത്ര പേജുകൾ അച്ചടിക്കാൻ കഴിയുമോ, അത്രയും പേജുകൾ മെഷീൻ B യ്ക്ക് 1.5 മണിക്കൂറിനുള്ളിൽ അച്ചടിക്കാൻ കഴിയും.1 മണിക്കൂറിനുള്ളിൽ മെഷീൻ B യ്ക്ക് എത്ര പേജുകൾ അച്ചടിക്കാൻ കഴിയും?