Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?A22 daysB20 daysC24 daysD18 daysAnswer: C. 24 days Read Explanation: This is an inverse proportion problem. If you decrease the number of typists, it will take longer to complete the same amount of work.Here's how to solve it:Total work: 6 typists * 16 days = 96 "typist-days" (This represents the total amount of work to be done)Days for 4 typists: 96 typist-days / 4 typists = 24 daysTherefore, 4 typists will take 24 days to complete the same work. Read more in App