Challenger App

No.1 PSC Learning App

1M+ Downloads
The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in ______ days.

A5.5

B5.75

C5

D5.25

Answer:

A. 5.5

Read Explanation:

Let number of days taken by B = x

Then:

  • A takes double → (A = 2x)

  • C takes half → (C = \frac{x}{2})

Given: A takes 12 days
2x=12x=62x = 12 \Rightarrow x = 6

So:

  • A = 12 days → work/day = ( \frac{1}{12} )

  • B = 6 days → work/day = ( \frac{1}{6} )

  • C = 3 days → work/day = ( \frac{1}{3} )

    Work done in 3-day cycle (B, A, C):

16+112+13\frac{1}{6} + \frac{1}{12} + \frac{1}{3}
LCM = 12:
=2+1+412=712= \frac{2 + 1 + 4}{12} = \frac{7}{12}
After 3 days → work done = (712)( \frac{7}{12} )

Remaining work:
1712=5121 - \frac{7}{12} = \frac{5}{12}
Day 4 (B works):

51216=512212=312=14\frac{5}{12} - \frac{1}{6} = \frac{5}{12} - \frac{2}{12} = \frac{3}{12} = \frac{1}{4}
Day 5 (A works):

14112=312112=212=16\frac{1}{4} - \frac{1}{12} = \frac{3}{12} - \frac{1}{12} = \frac{2}{12} = \frac{1}{6}
Day 6 (C works):

1613work finishes\frac{1}{6} - \frac{1}{3} \Rightarrow \text{work finishes}

C completes the remaining work in:

1613=12 day\frac{\frac{1}{6}}{\frac{1}{3}} = \frac{1}{2} \text{ day}

Total time:

5+12=5.5 days5 + \frac{1}{2} = 5.5 \text{ days}


Related Questions:

A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C , B alone can do the work in :
The ratio of efficiencies of 2 workers , P and Q is 5:2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone ?
ഒരു വാഹനം യാത്രയുടെ ആദ്യത്തെ 120 കി.മീറ്റർ ദൂരം ശരാശരി 30 കിമീ/മണിക്കൂർ വേഗത്തിലും അടുത്ത 120 കീ മീറ്റർ 20 കിമീ/മണിക്കൂർ വേഗത്തിലുമാണ് സഞ്ചരിച്ചത് . എന്നാൽ മുഴുവൻ യാത്രയിലെയും ശരാശരി വേഗം എത്രയാണ് ?
A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C, B alone can do the work in:
A, 6 ദിവസം കൊണ്ടും B, 12 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. ഒരുമിച്ചു പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് ജോലി തീരും?