Which of the following artificial activity suggests that an activity following it cannot happen unless, the previous activity is completed?

AEvent

BDummy

CConstant

DFree float

Answer:

B. Dummy

Read Explanation:

A dummy activity is used in a network diagram when there is no real activity between two events, but an event cannot occur until another activity has occurred. It does not consume resources or time duration.