Which of the following artificial activity suggests that an activity following it cannot happen unless, the previous activity is completed?
AEvent
BDummy
CConstant
DFree float
Answer:
B. Dummy
Read Explanation:
A dummy activity is used in a network diagram when there is no real activity between two events, but an event cannot occur until another activity has occurred. It does not consume resources or time duration.