Which of the following is a technique used for forecasting?

APERT/CPM

BExponential smoothing

CGantt Chart

DControl Chart

Answer:

B. Exponential smoothing

Read Explanation:

75. Forecasting is estimating the future value of a parameter using past data. Exponential smoothing, which gives weight to all previous data with highest weight to the most recent data, is a commonly used method. PERT and CPM are network techniques for planning, scheduling and controlling large projects. Gantt charts are used for resource planning and control charts indicate whether a process is in control or out of control and ensure product quality.


Related Questions:

During the development of a product an entirely new process plan is made based on design logic, examination of geometry and tolerance information. This type of process planning is known as
Which philosophy eliminates sources of manufacturing waste by producing the right part in the right place at the right time?
The full form of ERP is
The rule used for numbering events involved in project scheduling network is
Jobs going behind the schedule are conveniently shown in