X and Y can complete a piece of work in 8 days and 12 days, repectively. If they work on alternate days, with X working on the first day , how long will it take the duo to complete the same work?

A925days9\frac{2}{5}days

B935days9\frac{3}{5}days

C923days9\frac{2}{3}days

D912days9\frac{1}{2}days

Answer:

912days9\frac{1}{2}days

Read Explanation:

X can do the work in 8 days

Y can do the work in 12 days

LCM of 8 , 12 is 24

Total work =24

.Efiiciency of X = 248=3\frac{24}{8}=3

Efficiency of Y = 2412=2\frac{24}{12}=2

Working on alternate days start with X

3+2 = 5 work done on 2days

in 4days 10 work done

in 6 days 15 work done

in 8days 20 work done

in 9days 23 work done

Remaining 1 work done by Y

9+12=912days9+\frac{1}{2}=9\frac{1}{2}days


Related Questions:

Midhun writes the numbers 1 to 100. How many times does he write the digit'0' ?
മനുവിന് ഒരു ജോലി ചെയ്യാൻ 10 ദിവസം വേണം അനുവിന് അത് ചെയ്ത് തീർക്കാൻ 15 ദിവസം വേണം. എങ്കിൽ രണ്ടു പേരും ചേർന്ന് ഈ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?
A - യ്ക്ക് ഒരു ജോലി ചെയ്യാൻ 35 ദിവസവും, B-യ്ക്ക് അതേ ജോലി ചെയ്യാൻ 45 ദിവസവും ആവശ്യമാണ്. A - യും B - യും കൂടി ആ ജോലി 7 ദിവസം ചെയ് തു. അതിനുശേഷം A പോയാൽ ബാക്കി ജോലി B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും?
Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?