Challenger App

No.1 PSC Learning App

★
★
★
★
★
1M+ Downloads
A and B together complete a work in 8 days. If B is 25% more efficient than A, then in how many days will A alone complete the same work?

A12 days

B18 days

C24 days

D6 days

Answer:

B. 18 days

Read Explanation:

A+B = 8 days A/B=4/5 efficiency of A is 4 and efficiency of B is 5 so the efficiency of A&B is 4+5=9 total work is =9 x 8=72 A alone complete the same work = 72/4=18 days


Related Questions:

51 men can complete a work in 12 days. Four days after they started working 6 more men joined them. How many days will they now take to complete the remaining work?
A tank is filled in 4 hours by three pipes A, B and C. Pipe C is twice as fast as pipe B and pipe B is twice as fast as pipe A. How much time will pipe A take to fill the tank?
X can complete a task in 15 days, and Y can complete the same task in 20 days. If X and Y work on alternate days starting with X, in how many days will the work be completed?
ഒരു ജോലി Aയും Bയും ഒരുമിച്ച് ചെയ്തുതീർക്കുന്നതിന് 30 ദിവസം വേണം. Bയേക്കാൾ 3 മടങ്ങ് ജോലി ചെയ്യുന്ന ആളാണ് A. എങ്കിൽ A തനിച്ച് ആ ജോലി ചെയ്തുതീർക്കുന്നതിന് എത്ര ദിവസം വേണ്ടിവരും?
P, Q എന്നിവർക്ക് ഒരു ജോലി ഒരുമിച്ച് ചെയ്തുതീർക്കുവാൻ പന്ത്രണ്ട് ദിവസം വേണം. P-യ്ക്ക് ഒറ്റയ്ക്ക് ആ ജോലി തീർക്കുവാൻ പതിനഞ്ച് ദിവസം വേണമെങ്കിൽ Q-ന് മാത്രം ആ ജോലി തീർക്കുവാൻ എത്ര ദിവസം വേണം?