In linear programming problem, the term which is not involved is
Open
Question
A dummy activity is:
Open
Question
While solving a linear programming model, if a redundant constraint is added, then what will be its effect on existing solution?
Open
Question
Monte Carlo simulation of queues is used when
Open
Question
While doing the project planning of a Construction: project, using PERT, it is intended to identify the variance of the project. This can be done by:
Open
Question
In the Simplex method if in pivot column all the entries are negative or zero when choosing leaving variable then
Open
Question
In PERT analysis, a critical activity has:
Open
Question
The term 'jockeying' in queuing theory refers to
Open
Question
Consider the following statements in respect of PERT and CPM: Which of the statements are correct?
PERT is event-oriented while CPM is activity-oriented.
PERT is probabilistic while CPM is deterministic.
Levelling and smoothing are the techniques related to resource scheduling in CPM.
Open
Question
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-
Open
Question
In PERT analysis, the possible number of time estimates for activities linking up two events are -
Open
Question
In Emerson's efficiency plan of wage incentive system, the bonus is paid to-
Open
Question
Which of the following statements is FALSE about CPM?
Open
Question
Negative slack occurs when -
Open
Question
Which of the following distribution represents the time estimates in PERT ?
Open
Question
In queuing theory, the ratio of the mean arrival rate and the mean service rate is called the-
Open
Question
Slack represents the difference between the-
Open
Question
The amount of time by which an activity can be delayed without affecting project completion time is
Open
Question